Site view. Export of site soil complete. Shoring pile excavation in-progress. July 2021.
Installation of perimeter stabilization piles continues. October 2021
The downslope stabilization piles have been installed. December 2021
Stabilization piles 30 to 43 complete. Excavation to top of tie beam grade at completed pile pairs complete. Excavation of tie beam 43/46 initiated. Further trimming of temporary cut slope complete. January 2022
The second phase of upslope stabilization pile excavation is complete. May 2022
The third and final phase of upslope stabilization pile excavation is complete. August 2022
November, 2022: A portion of the basement has been excavated. Layout for the foundation is proceeding. Preparation for rakers along the north shoring wall is proceeding. Removal of slide debris, then replacement as compacted fill continues.